Impact fee credit transfers in Martin County, Florida
Martin County's code, rewritten in 2024, says credits are assignable and transferable between properties in the same or an adjacent district, and names no approver, form or procedure for a transfer. Creating a credit needs a Board of County Commissioners vote.
Six facts
Each one shows where we read it and how sure we are.
- Can a credit be transferred to another project?Yes
Ordinance 1230, adopted September 10, 2024, rewrote Article 6 and added transfer language that follows the statute, with no local approval step. The code sets out no transfer procedure. We read the text on a third-party copy of the code.
From a secondary sourceSource: zoneomics.com
- Who approves the transfer?Not specified in the code
Creating a credit needs a Board of County Commissioners vote (s. 6.11.B.2 of the Land Development Regulations). The code then says credits are assignable and transferable between properties in the same or an adjacent district (s. 6.11.B.10) and names no approver, form or procedure for a transfer.
From a secondary sourceSource: zoneomics.com
- How is a credit applied to a permit?Not yet verified
The fee payer must claim the credit before the permit is issued. The mechanics are not described in the code.
Not yet verifiedSource: zoneomics.com
- When is the fee due?At the building permit
When the building permit is issued, renewed or extended. Affordable housing builders may ask to defer until the certificate of occupancy or one year after the permit, whichever is earlier.
From a secondary sourceSource: zoneomics.com
- Do credits expire?No expiry found
No expiry was found for contribution credits. A different credit, given in place of a refund when a permit lapses after the fee was spent, runs with the land for ten years.
From a secondary sourceSource: zoneomics.com
- Is a credit worth dollars or a locked-in rate?A locked-in rate
The fee schedule steps up each January through 2028, and the code confirms that holders keep the full benefit of earlier credits after an increase.
From a secondary sourceSource: zoneomics.com
Fee districts
A credit can pay a fee in its own district or, under state law, an adjoining one.
- Park and fire fees
- One countywide district.
Transportation fees use benefit districts shown in a figure in the code, whose count we did not find. Fire, law enforcement, public buildings, libraries, parks and open space are each one countywide district.
From a secondary sourceSource: zoneomics.com
A move to an adjoining district
Allowed when the receiving parcel benefits.
From a secondary sourceSource: zoneomics.com
Typical time to close
We have no measured closing time for Martin County. The only county with measured figures so far is St. Johns.
Closing steps
In order, with who acts at each one.
We have not confirmed how Martin County closes a transfer. These are the standard steps, shown until the county confirms its own.
Credit holder and developer both sign the purchase agreement
The credit holder and the developer agree a price and both sign the purchase agreement.
Credit holder and DeveloperCounterhall re-confirms the unused balance with the county
The county's ledger is the only authoritative record of how much of a credit is unused. Counterhall checks the balance with the county again before the developer's money goes into escrow.
CounterhallClosing attorney confirms the purchase price is in escrow
The developer sends the purchase price to the closing attorney, who confirms when it has arrived. Counterhall never holds it.
Closing attorneyCounterhall files the transfer packet with the county
Counterhall sends the county what it needs to consider the transfer.
CounterhallCounty approves or accepts the transfer
The county decides whether the credit may be used for the receiving project.
CountyCredit holder delivers the signed and notarized assignment
The credit holder signs the assignment before a notary and delivers it.
Credit holderCounty confirms the credits have been transferred
The county records that the credit now covers the receiving project or its fee.
CountyClosing attorney confirms the credit holder and Counterhall's fee were paid
After the county has confirmed, the closing attorney pays the credit holder, and pays Counterhall's fee out of the credit holder's proceeds.
Closing attorneyDeveloper applies the credit to the fee
The developer uses the transferred credit to pay the fee.
Developer
What still needs confirming
- Martin's code makes credits transferable but names no approver, form or procedure. Ask the County Administrator's office how to file an assignment.
- A credit must be claimed before the building permit is issued.
- A credit can only offset the same category of fee.
- Our source for Martin County's transfer rule is second-hand or dated. Confirm the current rule with the county.
- Not yet verified for Martin County: how a credit is applied to a permit.
In every county
- The county must confirm the unused balance of the credit. Counterhall confirms it before a listing and again before the developer funds escrow.
- The credit agreement may add its own limits on where and how the credit can be used. Someone has to read it before closing.
- The receiving parcel must benefit from the improvement that created the credit. State law requires it and the county decides it.
Ask about Martin County
You owe a fee here
Send the project address and when you expect to pay.
Email us about a feeor write to max@earlyco.ai
You hold credits here
Send the name on the credit agreement.
Email us about your creditsor write to max@earlyco.ai
Last reviewed November 18, 2026.
This page is general information, not legal advice. It records what we have read and what we have not. Confirm the rule with the county and your own lawyer before you rely on it.